Monday, August 01, 2005

Nolensville Power Supply Upgrade Coming 2007

Steel Pole High Tension Cables in 100-foot
Right-of-Way to be In-Service June, 2007

A new power trans-
mission line would go 6 miles from Triune
Substation to Middle Tennessee's new pro-
posed substation on Williams Rd.just south
of Clovercroft. TVA says line is needed to
meet the sudden growth in Nolensville area.
Population may very well double in 2 years,
3,000 and more homes, a new school and
commercial buildings are being con-
structed. In June 2005 the above route was
deemed to be the preferred route
. This
summer they will be contacting property
owners for permission to begin field surveys
and environmental reviews all to be completed
Summer 2006. Fall 2006 begin right-of-way
acquisitions and begin in line service, June 2007.
Here is where to click on TVA web site for more
information and a map.
Attention: Nolensville...
is this exactly where you local land owners want
the lines to go? Let us know if you have been
contacted and how you feel about the route?
Email us hezakiah23@hotmail.com and we
will publish your comments so that others
become informed ASAP.